Roadwork Scheduled - Expect Delays!

Pickens Street - Milling and Paving
roadwork sign

Roadway work is expected to begin in Lakeville, weather permitting, Wednesday, May 24th.  Contractors will be using the Mill and Overlay process on the existing road.  

The tentative schedule is as follows:

Milling - Wednesday, May 24th and Thursday, May 25th

Paving - Tuesday, May 30th and Wednesday, May 31st

These dates have been revised from the original construction notice.

Residents of Pickens Street are asked to locate and flag existing sprinkler heads that are within ten feet of the roadway edge.  The Town of Lakeville is not responsible for the replacement of sprinkler heads or systems that are broken during construction but every effort will be made to avoid them if they are flagged. 

Police details will be onsite throughout the project to assist with traffic flow and safety.  There will be a rough road surface after milling, please use caution when traveling.  The top course of pavement will require additional time to set and road closures will be necessary to protect the integrity of the newly paved surface.  Marked detours will be in place. We are asking residents to exercise patience and use alternate routes whenever possible. 

Updated information will be posted on the Town website and the DPW Facebook page. 

AttachmentSize
PDF icon pickens_street_construction_notice.pdf147.82 KB