Roadwork Update from the Highway Department Tuesday 8/13/19

The Lakeville Highway Department will be conducting the following roadwork.  These dates are subject to change due to weather.

  • Tuesday 8/13 = Assawompset School Milling of the school driveways and parking lots will begin, possibly carrying over into the 14th.
  • Tuesday 8/13 = Animal Control parking lot Grading of lot will be done to prep the site for pavement.
  • Wednesday 8/14 = Precinct Street (from Montgomery St to Rte. 79) All structures will be raised to prep road for pavement. (Structures= Catch Basins, Manholes, etc.)
  • Wednesday & Thursday 8/14-8/15 = Precinct St. (from Montgomery St. to Rte. 18) Cold in Place Recycling process will be done. If you would like to  learn more about the Cold in Place process see attached link.  https://indusinc.com/roads/cold-in-place-recycling/
  • Monday 8/19 = Freetown St (from County Rd to roughly 14 Freetown St) Reclamation down to gravel and regraded to prep for pavement.

8/19-8/24 = All the following will be Paved;

  • Entirety of Precinct Street
  • Freetown Street Reclamation area only
  • Assawompset School driveways and parking lots
  • Animal Control parking lot

If there are any questions regarding any of this roadwork, or any other work being done in Town by my Department, please feel free to reach out to me directly.

Thank You,

Franklin Moniz

Highway Superintendent

Town Of Lakeville, MA

508-947-9521